This post contains pictures for the week ending August 18th, 2013.  The lower level underslab sewer has passed inspection and is being backfilled.  Once completed, the lower level footings will be excavated.  The upper level footings have been completely excavated, including the rocks that were blasted.  The sewer tank has been relocated to an area adjacent to the building where there is enough slope to meet code requirements.