This post contains pictures for the week ending September 29th, 2013.  The upper pad footings and steam walls are ready for concrete.  We passed our inspection today and the pour is scheduled for Monday.  The first truck will have color in the concrete to create samples for approval for the slabs.  The lower pad tall stem walls have been formed on the exterior portion.  The steel reinforcing is being placed and once complete, the interior portion of the walls will be formed.  The steel embeds for the structural steel columns are installed for the upper pad.