This post contains pictures for week ending November 16th, 2014.  The underslab insulation has been sprayed, and the wire mesh placed for the hydronic tubing installation.  Hydronic manifolds have been installed and tubing runs are underway.  The remaining exposed areas of the driveway and entry courtyard have been paved with asphalt for the winter.