This post contains pictures for week ending December 7th, 2014.  The slab was po0ured before the Thanksgiving holiday and covered to allow curing.  Due to wet rainy weather, framing was delayed at the beginning of the week last week.  The sill plates have been installed for the walls, and the framing has commenced at the garage.