This post contains pictures for week ending August 24th, 2014.  Utility trench excavation is underway with the electric and gas sleaving in place.  The amount of rock encountered is causing slower than anticipated progress.  The trench across the driveway has been backfilled and compacted.  Sewer lateral tie-in has been exposed, and trenching begun.  Rockery retaining walls at the driveway are being installed.