This post contains pictures for week ending October 23rd., 2015.  The first round of the Interior painting of the house is just about complete.   The Installation of the Knee Brace Hardware at the post & and beam areas has been completed.  The Masonry is progressing on the Post base areas of the house along with the fireplace chases and wainscot.    Masonry has started on the columns at the Garage.  Staining of the Game Room Terrace is complete.  Interior doors are onsite and ready for the installation process to begin.  The Garage Doors were installed this week. The boiler in the Mechanical room has been installed and is running.