This post contains pictures from the week ending July 17, 2016.

We are reaching the end of this fantastic journey.  This week all of the finishing touches are being placed.  Driveway final lift was completed.  Landscaping in and running (Looks great Mr. Blide). AV components installed and working nicely.  All carpet is in. Furniture that is onsite has been staged with more arriving daily. Main Guard and Grip rail system is complete including the wood cap.  Robert has provided several pictures showing the various rooms staged with furniture that is onsite now. Pictures showing the completed Bunk, walls awaiting covering material selection.

Everyone please have a wonderful weekend and we’ll see Wednesday for the formal move in.