This post contains pictures from the week ending June 19, 2016.

Wine room wood work is complete with just the Glass and Mirror work to finish it off.  All of the prep work to receive the wall paper in the Media Room is complete.  The Great Room casework installation is almost complete.  Finish paint and stain is moving throughout the house.  Again for this week, the Appliance installation is being shown in several pictures.  More pictures of the Drainage System installation as work on it continues.  The Gutter Downspout chains have been installed along with the Heat Tape.  The main interior guard rail installation continued this week and is almost complete.  The wire mesh for the lockers has been installed.  Mirrors for the bathrooms are being installed.

Everyone please enjoy your Weekend.