This post contains pictures from the week ending June 28, 2015. This week there are several pictures showing the electrical, fire suppression and insulation being placed in the remaining roofing over build areas. Beam wrap and decking continues at the covered Game Room terrace.  Robert has taken several pictures of the Acousti-Mat & Hydronic tubing.  Crestwood also uses this as documentation for the lay out as well. Siding, Soffit & Trim work progressing nicely.  Lastly Robert has at Dave Conte’s request, taken a few pictures from the entry area of the driveway looking towards the house.