This post contains pictures from the week ending May 1, 2016.

90 % of the Decretive Light Fixture Package is now on site and installation has begun in the areas ready for them.  The casework for the Master Bedroom Closet is complete except for the placement of the drawer & door faces.  Installation for the Wine room has started this now that most of the prep work done.  Baseboard installation is in progress where the wood floors have been completed.  The Isokern insert unit has been placed and access to the internal components is being shown.  Mechanical room components are continuing to be installed.  Plumbing fixtures are being installed throughout the house as well.

Everyone please enjoy your Weekend.