This post contains pictures from the week ending May 15, 2016.

The Decretive Light Fixture installation is continuing and progressing nicely.  The decretive metal footrest for the Conte bar had been installed.  Installation of the Wine Room Lid materials is in progress.  Baseboard installation continues, and we are showing the finishes that were applied in some of our pictures for this week.  The Great Room glazing unit is on site and installation is scheduled for Monday.  The masonry for the Great Room fireplace started this week.  Paver installation on the back yard terraces is coming along.  The wood stair treads to the Guest Loft installation is complete.  The first phase of the Bunk Bed casework installation is being shown.  Finishes for these will be done on site.

Everyone please enjoy your Weekend.