This post contains pictures from the week ending October 18, 2015. Interior painting is still in progress throughout the house.   The Installation of the Knee brace Hardware at the post & and beam areas is almost complete.  The Masonry is progressing on the Post base areas of the house along with the fireplace chases and wainscot.    The Gas Meter from South West Gas has been set. The Production of the AC/Generator screening walls is still ongoing awaiting the cap material to complete.  There are Pictures of the completed beam wraps at the Game Room Terrace and the Painters have started the process of staining them.  Interior doors arrive next week and then the installation process can begin.