This post contains pictures from the week ending September 13, 2015. The Generator and A/C screening areas with concrete pads are complete.  Drywall Tape & Texture is in full swing and ongoing.  The Ipe decking for both of the upper balconies installation is in progress along with the deck posts.  Game Room Terrace rafter Fir wrapping is still ongoing.  Exterior siding and trim work is nearing completion. The Installation of the Knee braces at the post & and beam areas is under way. View of the completed exterior soffit over the auto port.