This post contains pictures from the week ending September 27, 2015. The Drywall tape & texture is nearing completion.  Game Room Terrace rafter Fir wrapping is complete.  The Installation of the Knee braces at the post & and beam areas is also nearing completion.  Masonry has begun on the Post bases at the Entry areas of the House.  AC/Generator screening walls are in production.  Steel Kick plates were installed on all of the lower panels of the Garage Doors.