This post contains pictures for week ending June 16th, 2013.  The door, window, and base trim installation at the lower level is nearly complete.  The doors and trim upstairs and in the kitchen have been stained.  Hardwood flooring has been installed on the stairs and upper landing.  Deck rail accents have been installed, and the wire inserts are onsite for installation.  The masonry veneer at the firepits and rear terrace walls is underway.