This post contains pictures for week ending June 9th, 2013.  The remaining exterior outlookers and knee-braces have been stained.  The electrical switches and outlets are being installed.  The kitchen hood surround has been installed, and the tile backsplashes completed.  Fireplace chimney masonry has been completed and the exterior wall veneer and cap is in progress.  The staircase railing and wood treads and risers have been installed.

[flickrset id=”72157633987566603″ thumbnail=”small” photos=”” overlay=”true” size=”medium”]