This post contains photos of the week ending October 13th, 2013. The frame of the garage and mudroom is underway, with the roof framing nearly complete. The wood sub-floor was prepared for concrete by installing the wall plates. Our electricians completed their under slab preparations by placing the floor outlets in the pavilion. Sierra insulation installed the under slab insulation at the pavilion and mudroom. Weiland is under contract, and we will be receiving the 6-panel shop drawings this week (Oct 14-18). Sierra Pacific windows are in review, with the order to be placed this Thursday (Oct 17). RGA has refined the concrete floor finish details, and the Weiland installation.