This post contains photos of the week ending October 20th, 2013. Framing Sub-Contractor (RO) framed out the garage, and the roof was inspected and approved for cover. Crestwood (CW) and RO reviewed the window proposal and Weiland shop drawings for ordering- awaiting a revision from RGA. Our plumber (ProH2O) installed hydronic tubing on the remaining floor areas.  The Concrete Sub-Contractor (BJC) prepped the floors for slab pour on Tuesday (10-22-13). RO and CW installed the steel detailing for the slab.