This post contains photos of the week ending November 3rd, 2013. The week started off with 8 inches of snow covering the lot. So Monday was a snow clearing day, with the framers returning on Tuesday. They managed to build the floor for the Master Wing, and are currently framing the walls on the main house. The roofers dried-in the garage roof. The structural steel welding crew completed welding the Master Wing’s floor system, and the remainder of the steel is in production for a scheduled steel set this coming Thursday (11-7-13).