This post contains photos of the week ending September 15th, 2013. Backfill and final grade began this past week. The driveway was prepped and paved. Steel shop drawings were completed. The steel will be in production this coming week (16th-20th), and delivery and install will begin thereafter. Garage slab prep is underway, to be poured this coming week (16th-20th). Framing at the garage will begin after that.