This post contains photos of the week ending September 22nd, 2013. The excavator continued to backfill in and around the building. They finished out the week working on drainage. Sierra insulation insulated the perimeter of the living area slabs and the floor of the garage slab. Bobby Jones Concrete prepared the slab at the garage for installation of hydronic tubing. Pro H2o installed their manifolds and tubing for the in slab heat in the garage. Hunter Metal picked up the templates for the areas between gridlines 1 and 16. This steel is in production for delivery on 10-7-13. Our painter, Greg Glad, developed updated stain samples for next round of review.