This post contains photos of the week ending December 22nd, 2013. Framers worked on pick-up (interior and exterior), windows, and doors. The plumbing crew worked on the roof drains above the Pavilion. Tuesday December 17th, Crestwood and Ryan Group met out on site to walk the entire house and discussed framing questions, periscope window layout, and interior details. New plans were distributed by Ryan Group (12-17-13) as a result.

[flickrset id=”72157639092782566″ thumbnail=”small” photos=”” overlay=”true” size=”medium”]