This post contains pictures from the week ending January 29, 2017.

We can see progress on the soffit installation and drywall taping. We received tile delivery for Phase 2 this week and we can see the progress on tile setting. Snow shoveling continues through the week to gain construction access. We had site meetings on Thursday and Friday with Denise Kuriger and subcontractors. We have pictures that show samples of the wallpaper for South Bunk, Guest Bedroom #3, Guest Bedroom #1 and Master Bath.