This post contains pictures from the week ending July 31, 2016.

We see progression on the air barrier installation that is part of the exterior skin of the building (RainDrop 3D). We are moving forward on window installation. Clerestory windows are being installed.  Forms on the concrete walls above the roof can be seen in the pictures. From last week, we can see the eave at the main living/dining area east elevation being furred out. The installed roof frame at the main level can be seen. The entrance soffit is being wrapped up now. The exterior pictures also show the foam board insulation arriving on site. Pictures of the wood cabinet boards can be seen. While looking at the pictures of the interior elevation we see MEP rough in progression on the main level.”