This post contains pictures from the week ending November 6, 2016.

We can see the concrete pour progress for the backyard stairs.
We see the rough in wiring and openings in the soffit space for the Infratech heaters at the covered patio terrace areas.
Radiant heating manifold is being laid out for the floor at the Upper Level.
Photos of the new gas meter that was installed on Monday can be seen.