This post contains pictures from the week ending October 18, 2015.  The construction lift of the asphalt driveway has been placed.  The excavation for the foundation footings is ongoing.  The concrete contractor has begun laying out grid lines and setting up the batter boards.  Steel reinforcement, rebar, will be starting soon for the footings.