This post contains pictures from the week ending September 18, 2016.

Rough Mechanical, Plumbing, and Electrical continues.   The HVAC line sets have been run and tested.  The wall furr outs and soffit framing has begun and continues.  Max’s bathroom window has been set as well as Alex and Guest room sliding doors have been installed.