This post contains pictures from the week ending August 21, 2016.

The garage is painted, and the painters will start the upstairs primer soon. We are about to begin installing tile on the exterior terraces. The drywall texture crew is installing the metal reglet detail at the base of all the walls and finishing up their scope. We are focusing on the siding and trim surround for the Hot Tub, per the RGA details. Landscape installation continues.