This post contains pictures from the week ending August 14, 2016.

Meg, Stu and Family, this week work concentrated on all of the under floor Mechanical elements.  Plumbing and Venting were completed and Inspected.

Part of the Inspection process covered the insulation of the Duct Work System, shown in several of this week’s pictures.  You can see in the pictures where all of the Water Lines have been insulated as well.  Now that Inspections are complete, floor sheeting can begin.

There are few pictures showing the Floor Drains that will be incased in the Garage floor concrete.

Have a wonderful weekend.