This post contains pictures for the week ending February 26, 2017.

Meg, Stu and Family, this week we have pictures for Exterior Siding, Insulation, Weiland Doors, Drywall Return prep and Drywall Installation.

Siding continued this week despite Mother Nature throwing us another round of snow and rain.

Insulation continues and is expected to be complete by Friday.  We lost 2 days for installation; Monday – Presidents holiday – and Tuesday – snow –

The installation of the Weiland doors started this week.  Completion should be sometime next week.

Drywall Return preps continues for the CW carpenters.

The hanging of the Drywall has begun with the Garage starting first.  This will allow us to get the Garage doors hung.

Have a wonderful weekend.