This post contains pictures from the week ending July 24, 2016.

Meg, Stu and Family, this week framing continue on the lower level floor assemblies.  Shear panels were placed for lateral stability on the lower pony walls where engineering required.  There are several pictures showing the floor joist being installed.

The first lift of Asphalt was placed this week.  The second and final lift comes at the end of the project.  You can see this process in a few of the pictures.

Water filtration assemblies are shown in a few pictures as well.  These are placed to grab water from the uphill side of the structure so that it can be released on low side.

Structural steel deliveries started this week with some of the members already being placed.

Have a wonderful weekend.