This post contains pictures from the week ending July 3, 2016.

Meg, Stu and Family, this week all of the foundation concrete was placed.  The concrete forms for the East side of the house were completed and inspected this week.  Concrete was then poured.  The forms where stripped the following day.   For the already finish taller stem walls, the water proofing application process began.  You can see in some of the pictures, the areas where we added PVC sleeves under the forms before pouring.  We do this to supply a way to get pluming, sewer and electrical to different areas of the house.  There is a picture showing rebar epoxied to the boulder that was in our footings.  They call this pinning the rebar.

Please everyone, have a safe and wonderful Fourth of July and we will see you next week for our site meeting.