This post contains pictures from the week ending June 11, 2017.

Meg, Stu and Family, this week we have pictures showing the Roofing, Interior Ceiling work, Cabinet installation and the Hydronic panel covers.

Roofing is steadily making progress and has now moved to the lower pitches.

Ceiling installation moved to the Kitchen area to stay ahead of the Cabinetry.  Cabinets for this area are expected to arrive sometime next week.

The first phase of Cabinets arrived this week – wet areas – and installation has begun.

Lastly, Kurt has provided us with the Finished look for the Hydronic Manifold Covers.

Have a wonderful weekend.