This post contains pictures from the week ending June 19, 2016.

Meg, Stu and Family, this week the trenching for the foundation footings was completed. Rebar is now being placed in the footings and work on forming of the stem walls has begun.  You can see from several of the pictures all of the material that is required for the foundation.  As you can see, some of these walls are quite high in order to retain the exterior grade.  You can also see just how much re-bar that is required for the foundation.

Hope you’re having fun on your vacation.  Please enjoy your Weekend and will see all of you soon.