This post contains pictures from the week ending June 26, 2016.

Meg, Stu and Family, this week all of the tall foundation retaining walls located on the Westside of the house (Garage through the North Suite) were completed.  We then had them inspected by our Building Dept. and concrete was then poured on Thursday.  This was the completion of Phase One.  We will complete phase two next Tuesday or Wednesday.  Phase two includes the Eastside of the House (from the Entry to the Master Bedroom).  We are now stripping the forms where the concrete was completed and will start the waterproofing this Saturday.

Please enjoy your Weekend and will see all of you soon.