This post contains pictures from the week ending March 19, 2017.

Meg, Stu and Family, this week we have pictures for Drywall Hanging & Snow Removal.

We have several pictures to show you this week of the Drywall processes.  Tape and Top along with the finish is mostly complete in the Garage area.  Hanging will be complete for the entire house this Saturday.  Tape & Top for this area begins Monday.

Work started last week on the removal of snow on the Roof areas.  You can see by several pictures just how much had accumulated over this wild winter.  Removal was completed on Wednesday.

Lastly, we have a few pictures showing the excavator removing the snow that came from the Roof areas.

Have a wonderful weekend and will see you next Friday.