This post contains pictures from the week ending November 5, 2017.

Meg, Stu and Family, this week we have pictures showing: Paint and Stain Work, Shower Glass, Tile Work, Case Work, Exterior Tub and A/C Corals along with the BBQ Station and Wood Stair Risers.

Paint and Stain work is showing movement throughout the House.  Doors were completed this week.  Ceilings were completed.  Case and Base is in the works for the areas that are complete.  Can Light Trims are now painted.

Shower Glass has been installed in the Master and North Suite Showers.

Tile work continues with the Laundry, Kitchen and West Bath being shown.

The Bunk Room Case Work installation is complete now and waiting for the finishes to be applied.

The Exterior Tub Surround, A/C Corrals, and BBQ Stations are almost complete.

The Wood Floor for the Stair Risers is going in now.

Have a wonderful Weekend.