This post contains pictures from the week ending November 20, 2016.

Meg, Stu and Family, this week we have pictures showing the installation for the Dining Room and Great room replacement doors.

Placement of the Ceiling Cans is ongoing.  Head outs for those ceiling cans is mostly complete as well.

Drop Ceiling in the North Suite Bath is complete along with the overhead platform in the mechanical room.

Trench work for the gas line to the portable patio heater at the Dining Room terrace was also completed this week.

Everyone please enjoy your weekend.