This post contains pictures from the week ending October 30, 2016.

Meg, Stu and Family, this week we have pictures showing the progress for the Electrical portion of the MEP’s.

Kurt has also identified all the areas in the ceiling where Head Outs in the framing will be needed to place the Light Fixtures over the designated area (not shown).  Out framing contractor has begun some of this work already.

Once the Electricians have progressed to a certain point, we will be calling in the Plumbing, HVAC and Fire Suppression sub-contractors to start their portion of work.

Weather has once again moved into our area producing much needed amounts of rain.

Please enjoy your weekend.