This post contains pictures from the week ending September 3, 2017.

Meg, Stu and Family, this week we have pictures showing Soffits, Accent Walls, Ceiling, Trim and Tile Work.

Exterior Soffit work has been completed around the outside of both Garage Doors.

The Redwood Accent Materials are just about complete at the Stair Column.  The Walnut Cubbies have been completed as well with the Walnut Cap left to install.

Work on the Media Room Ceiling is progressing.  Kurt has provided a few pictures showing this.

Window Sill work is in progress around the Upper Great Room Windows.

Landscape prep work started this week. They are concentrating in the areas that will not impact other subs for now.

Have a wonderful Labor Day Weekend.