This post contains pictures from the week ending October 16, 2016.

Radiant tubing is being installed on the lower level and the driveway is being graded and compacted in preparation for the 1st lift of asphalt.  Underground utility work continues.  Soil stabilization is being put in place in anticipation of inclement weather.

Have a wonderful weekend!