This post contains pictures from the week ending August 07, 2016.

Our team is rolling the elastomeric waterproofing membrane on the exterior concrete walls.  The black rolls of drainage board are on-site and will be installed once the roll-on waterproofing has been completed.  Waterproofing is on-going.  The temporary power pole has been installed this week as well.