This post contains pictures from the week ending August 14, 2016.

Our team has finished rolling the elastomeric waterproofing membrane on the exterior concrete walls and installed the drainage board.  Installation of the perforated drain pipe and drain rock is underway installed.  We also have a picture of the concrete form boards in the process of being removed from the interior side of the concrete walls.