This post contains pictures from the week ending September 4, 2016.

Slope stabilization is being installed on the large cuts and the rebar is being formed for the lower level.  Backfill of the retaining wall areas continues.  The forms have been stripped from a portion of the retaining walls as well.

It seems we had a small visitor (ground squirrel) watching the work this week!

Have a wonderful holiday weekend!