This post contains pictures from the week ending August 14, 2016.

Roof insulation is installed and preparing for inspection. Beginning to sheath the roof in preparation for dry-in. Framing crew is working to prepare for 1st phase window installation. Pool installation has begun. Mock-up review for Site Wall Design (with Martis Camp ARC) is scheduled for Monday, August 15th.