This post contains pictures from the week ending July 31, 2016.

The built-up roof is installed, and next week we will begin spray insulation into the roof cavity. We will begin to install garage drains next week, in preparation for future Garage slab pour. The pool + Spa have been excavated, and we plan to start install with Robert Allen Pools + Spas as soon as the Placer County permit is issued.