This post contains pictures for the week ending November 10th, 2013.  The foundation has been back filled with base rock with a conveyor belt and then compacted.  The next step will be to place 2″ of insulation, place the rebar and hydronic tubing, then the final electrical and HVAC components such as floor boxes and the supplemental in floor heating and cooling units.