This post contains pictures from the week ending May 20, 2018.

There was a good start to the Cabinet installation this week.  This will allow us to get some of the Countertops Templated.

The Fireplace Wall Tile was completely installed this week.  The Entry Floor Tile, with it intricate pattern starts this Friday.

Pavers are all complete.  Bob is showing several pictures of the pavers at the Entry, Terraces and Pathway.

The last of the Pick-up Framing is being completed.

Lastly,  Bob is showing, in the pictures, the completed looks for the Exterior.

Have a wonderful weekend.