This post contains pictures from the week ending February 25, 2018.

  • Insulation is complete. Bob has provided several pictures showing the Blown In and batt insulation throughout the house.
  • The Party Time Fireplace was installed this week.
  • Exterior Soffit work continues. Weather caused some slowdowns this week.  It’s looking like we are in a bit of a wet weather pattern for the upcoming week as well.
  • The Concrete pour was called off this week due to the low temperatures and precipitation.

Have a wonderful weekend.