This post contains pictures from the week ending March 11, 2018.

  • Exterior Siding continues to make good progress even with the March weather we’ve been receiving.


  • Interior Pick Framing will be done today ahead of Monday’s Drywall Installation.


  • Drywall Stocking was done on Wednesday of this week and Installation is scheduled for Monday of next week.


  • Brackets for the Floating Shelves have all been installed.


Have a wonderful weekend.